1. HDPE Geomembrane Project Overview & Core Objectives
1.1 HDPE Project Background
This plan applies to the anti-seepage engineering of waste dumps, aiming to install high-density polyethylene (HDPE) membranes as the core anti-seepage layer. The typical laying area covers the dump bottom, slopes, and surrounding catchment ditches, with the HDPE membrane thickness designed as 1.5-2.0mm. The key technical requirements include: permeability coefficient ≤1×10⁻¹³ cm/s, weld strength ≥80% of the base material strength, and zero leakage risks during service.
1.2 Core Objectives
- Quality Compliance: Achieve 100% integrity of the anti-seepage system with qualified third-party testing results.
- Safety Assurance: Prevent membrane damage and leakage accidents; ensure safe operation in complex environments (e.g., methane accumulation areas).
- Efficient Construction: Complete 800-1200㎡ of membrane laying per day, with the total construction period controlled within the planned schedule.
- Cost Optimization: Keep material loss rate ≤2% (HDPE membrane) and rework cost ≤8% of the total project cost.
2. Pre-Construction Preparation
2.1 Site Preparation
- Base Treatment: The base surface must be compacted (compaction degree ≥95%) with flatness ≤5mm/2m. Remove all sharp objects (e.g., stones larger than 5mm, tree roots, concrete debris) to avoid membrane puncture. For soft soil foundations, replace with gravel and level the surface.
2.2 Transportation & Storage
Transportation: Use flatbed trucks with rubber mats (thickness ≥10mm) on the carriage. Stack rolls ≤3 layers with wooden boards (thickness ≥20mm) between layers. Avoid transportation during high-temperature periods (11:00-15:00 in summer) and cover with sunshades or rain cloths as needed.
2.3 Equipment Preparation
- Core Equipment: Double-track hot-melt welding machines (power 3kW, temperature range 180-220℃), extrusion welding machines (for repairs), spark leak detectors (30kV), universal testing machines, and vibration rollers (12t).
3. Core Construction Procedures
3.1 Laying Principles & Methods
- Laying Sequence: Start from the bottom of the dump and proceed upward; lay slopes first, then the bottom. Align the HDPE membrane direction parallel to the maximum slope line.
- Tension Control: Avoid over-stretching; reserve 1.5-2.0% slack to accommodate settlement and temperature changes.
- Seam Arrangement: Longitudinal seams should be staggered by ≥1m and kept ≥1.5m away from slope bottoms or bends. Minimize seams at corners and irregular shapes.
- Temporary Fixing: Use sandbags to press the membrane immediately after laying to prevent wind displacement. For slopes and curved surfaces, use straps or expansion bolts for temporary fixation.
3.2 Welding Construction
3.2.1 Welding Conditions
- Environmental Requirements: Construct when temperature is 5-40℃, wind speed , and no rain/snow. Avoid welding at noon in summer (temperature ≥35℃).
- Preparación de la superficie: Clean the overlapping area (width ≥10cm) to remove dust, oil, and moisture (moisture content ≤5%).
3.2.2 Welding Process
- Test Welding: Conduct trial welding 7 days before formal construction in a 20㎡ test area. Determine optimal parameters through 3 groups of tests (recommended: temperature 200℃, speed 1.8m/min, pressure 0.35MPa).
- Formal Welding: Adopt double-track hot-melt welding for main seams; use extrusion welding only for repairs. Ensure welds are continuous without virtual welding or missing welding OF HDPE.
4. Supporting Measures
4.1 Quality Control Measures
- Document Management: Number each membrane roll and record the laying position, weld parameters, and inspection results.
- Process Supervision: Assign full-time inspectors to monitor base treatment, welding, and inspection. Implement a three-party confirmation system (construction, supervision, and environmental monitoring) for key processes.
- Defect Repair: Mark damaged areas immediately and repair with the same material. The repair lap width should be ≥200mm.
4.2 Safety & Environmental Protection Measures
- Safety Protection: Workers must wear anti-static clothing, gas masks, and non-slip shoes without sharp soles. Prohibit smoking and using sharp tools on the membrane.
4.3 Coordination & Collaboration Measures
- Inter-Department Collaboration: Establish communication mechanisms between construction, supervision, design, and environmental departments. Hold daily technical disclosure meetings to confirm construction parameters.
- Community Communication: Set up a communication group with surrounding communities to publicize deodorization measures and monitor data, reducing complaints.
- Emergency Response: Prepare emergency plans for leakage, methane accumulation, and severe weather. Ensure emergency response time ≤20 minutes.
4.4 Weather Adaptation Measures
- High Temperature: Avoid construction at noon; store membranes in shaded areas to prevent thermal deformation.
- Low Temperature: Compact membrane laying and use heating equipment for welding (if temperature is 0-5℃).
- Wind & Rain: Stop construction when wind speed ≥5 levels or during rain. Install temporary drainage ditches (spacing ≤8m) in rainy seasons.
5. Construction Schedule & Resource Allocation
5.1 Schedule Arrangement
- Preparation Stage (7-10 days): Material inspection, equipment commissioning, site cleaning, and safety training.
- Trial Construction (2-3 days): Test laying and welding in non-critical areas to optimize parameters.
- Formal Construction (30-50 days): Complete HDPE membrane laying, welding, and inspection with a daily output of 800-1200㎡.
- Acceptance Stage (3-5 days): Conduct third-party testing and rectify unqualified items.
5.2 Resource Allocation
- Personnel: 4-6 professional anti-seepage workers (with environmental operation certificates), 1 methane monitor, and 1 safety officer (trained in anti-toxic and explosion-proof skills).
- Materiales: Reserve 5% of additional membranes and auxiliary materials for repairs.
- Equipment: Equip backup welding machines and detectors to ensure continuous construction.